5. MAINTENANCE & INSPECTION
1) Replacement of Parts
1-1) Replacement of Switch
(1) Remove the four screws, and pull out the switch plate on the front.
(2) Remove the two screwsand remove the switch from the switch plate.
(3) Loosen the four screws, and remove the four lead wires to the Switch.
(4) Install the lead line to a new switch.
(5) Install a new switch, installed to lead line in the Switch Plate with the two screws.
(6) Install the Switch Plate in the machine with the four screws.
25
• Always wear gloves when replacing the Cutting Blade and Threading Dies.
Disconnect the Power Plug.
Disconnect the Power Plug to avoid electric shock.
34
Screw (1)
Screw (3)
lead line
Switch
Switch Plate
Screw (2)
Switch Cover
Switch Spacer