Commissioning
Fig.129: Lag monitoring
Commissioning the motor with the NC
Once the parameters are set, the motor is basically ready for operation. Individual further parameters
have to be adapted to the respective application.
To commission the axis, activate the configuration (Ctrl+Shift+F4), select the axis, select tab Online
and enable the axis under Set.
Set all tick marks and set Override to 100% (see Fig. Enabling an axis). The axis can then be moved.
EL72x1-0010102 Version: 2.0