HD-973P Series Multi-Level Parking Lift 14 P/N 5900076 — Rev. B3 — January 2024
Installation Checklist
Following are the steps needed to install your Lift. Perform them in the order shown.
☐ 1. Review the installation safety rules.
☐ 2. Make sure you have the necessary tools.
☐ 3. Plan for electrical work.
☐ 4. Select the installation location.
☐ 5. Decide the Lift Orientation.
☐ 6. Create Chalk Line Guides.
☐ 7. Unload and unpack the Lift components.
☐ 8. Move the Posts into position.
☐ 9. Install the Crosstubes.
☐ 10. Install the Ladders and Top Cap.
☐ 11. Raise the Crosstubes.
☐ 12. Raise the Posts.
☐ 13. Remove the Sheaves.
☐ 14. Secure the Ladders.
☐ 15. Install the Runways.
☐ 16. Route the Lifting Cables.
☐ 17. Install the Air Lines.
☐ 18. Install the Return Lines.
☐ 19. Install the Hydraulic Hoses.
☐ 20. Install the Safety Shutoff Bar and the Microswitch.
☐ 21. Install the Power Unit.
☐ 22. Install the Flex Tube Bracket Plate and Angle Plate.
☐ 23. Install the Flex Tubes.
☐ 24. Install the Pushbutton Air Valve and connect the Air Lines.
☐ 25. Connect the Return Lines.
☐ 26. Install the Platform Selector Valve and connect the Hydraulic Hoses.
☐ 27. Contact the Electrician.
☐ 28. Connect to a power source (Electrician required).
☐ 29. Connect the Microswitch (Electrician required).
☐ 30. Install the Power Disconnect Switch and Thermal Disconnect Switch (Electrician required).
☐ 31. Anchor the Posts.
☐ 32. Perform final leveling.
☐ 33. Install the Accessories.
☐ 34. Install the Crossbeams.
☐ 35. Lubricate the Lift.
☐ 36. Bleed the Hydraulic Cylinder.
☐ 37. Test the Lift.
☐ 38. Review the final checklist.
☐ 39. Leave the manual for the owner/operator.