EasyManuals Logo

BendPak XPR-9F User Manual

BendPak XPR-9F
52 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #29 background imageLoading...
Page #29 background image
29
POST-INSTALLATION CHECK-OFF
Columns Properly Shimmed And Stable
Anchor Bolts Tightened
Pivot / Sheave Pins Properly Attached
Carriage Stop bolts Torqued to 2-3 Ft.- Lbs
Electric Power Supply Confirmed
Cables Adjusted Properly
Safety Locks Functioning Properly
Check For Hydraulic Leaks
Oil Level
Lubrication of Critical Components
Check For Overhead Obstructions
Lift Arms Level
All Screws, Bolts, and Pins Secured
Surrounding Area Clean
Operation, Maintenance and Safety Manuals
on Site.
.
STEP 16
(Lubrication)
1. After installation and start up has been completed,
lubricate lift components as described below.
( See Fig. 16.1 )
NOTE:
THERE WILL BE INITIAL STRETCHING OF THE
CABLES AND/OR WITH INCREASED LOADS.
ADJUST THE CABLES AS OUTLINED ABOVE A
WEEK AFTER FIRST USE, THEN EVERY THREE TO
SIX MONTHS THEREAFTER DEPENDING ON USAGE
AND/OR TO COMPENSATE FOR STRETCH.
Fig. 16.1.

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the BendPak XPR-9F and is the answer not in the manual?

BendPak XPR-9F Specifications

General IconGeneral
BrandBendPak
ModelXPR-9F
CategoryLifting Systems
LanguageEnglish

Related product manuals