X7-4-Install-IG100 Installation Guide
Brocade
®
X7-4 Director Hardware Installation Guide
7. Reinstall the door. See the procedures for removing and replacing the device door in this guide.
Installing the 8U Chassis 27-31-Inch Rail Rack Kit for Four-Post Racks
(XBR-DCX4S-0120)
Time and Items Required
Allow approximately one hour to unpack and install a device in a rack.
The following tools are required to install the 8U Chassis 27-31 Inch Rail Rack Kit for Four-Post Racks (XBR-
DCX4S-0120).
Torque wrench with No. 2 Phillips screwdriver tip
Flathead screwdriver
Hydraulic or assisted lift with a minimum raise of 140 cm (55 in.) and a minimum capacity of 113 kg (250 lbs).
Parts List
The following parts are provided with the 8U Chassis 27–31 Inch Rail Rack Kit for Four-Post Racks (XBR-DCX4S-0120).
NOTE
Not all parts may be used with certain installations depending on the device type.
Figure 22: Rack Kit Parts
1. Left Rail
2. Right Rail
X7-4-Install-IG100
51