UNIT START-UP CHECKLIST
(Remove and Store in Job File)
I. PRELIMINARY INFORMATION
MODEL NO. __________________________________________________
JOB NAME ___________________________________________________
SERIAL NO..__________________________________________________
ADDRESS ___________________________________________________
START-UP DATE ______________________________________________
TECHNICIAN NAME __________________________________________
ADDITIONAL ACCESSORIES
_____________________________________________________________________________________________________
II. PRE-START-UP
Verify that jobsite voltage agrees with voltage listed on rating plate (Y/N) _____
Verify that all packaging materials have been removed from unit (Y/N) _____
Remove all shipping hold-down bolts and brackets per installation instructions
Verify installation of outdoor air hood (Y/N) _____
Verify installation of flue exhaust and inlet hood (Y/N) _____
Verify that condensate connection is installed per instructions (Y/N) _____
Verify that all electrical connections and terminals are tight (Y/N) _____
Check refrigerant piping for indications of leaks; investigate and repair, if necessary (Y/N) _____
Verify gas pressure to unit gas valve is within specified range (Y/N) _____
Check gas piping for leaks (Y/N) _____
Check that indoor-air filters are clean and in place (Y/N) _____
Check that outdoor-air inlet screens are in place (Y/N) _____
Verify that unit is level (Y/N) _____
Check fan wheels and propeller for location in housing/orifice and verify setscrew is tight (Y/N) _____
Verify that fan sheaves are aligned and belts are properly tensioned (Y/N) _____
Verify installation of thermostat (Y/N) _____
Verify that crankcase heaters have been energized for at least 24 hours (Y/N) _____
Check to ensure that electrical wiring is not in contact with refrigerant lines or sharp metal edges (Y/N) _____
Check pulley alignment and belt tension per installation instructions
III. START-UP
ELECTRICAL
Supply Voltage L1-L2_____________ L2-L3_____________ L3-L1_____________
Compressor Amps 1 L1 _____________ L2 _____________ L3 _____________
Compressor Amps 2 L1 _____________ L2 _____________ L3 _____________
Supply Fan Amps L1 _____________ L2 _____________ L3 _____________
Indoor Fan Amps ________________ ________________ ________________
Outdoor Fan Amps ________________ ________________ ________________
NOTE: To avoid injury to personnel and damage to equipment or property when com-
pleting the procedures listed in this start-up checklist, use good judgment, follow safe
practices, and adhere to the safety considerations/information as outlined in preceding
sections of this Service and Maintenance Instruction document.