When you know the amount of power that is required for operations (available power) and redundancy (reserve
power), you can plan for the required number of input power receptacles with reach of the switch location.
Step 1 Determine the power requirement for the switch by summing the maximum wattage for each installed module (see the
following table).
Table 1: Power Requirements for the Cisco Nexus 7710 Switch Modules
TypicalMaximumQuantityComponent
1 or 2 (same type if
using 2)
Supervisor Modules
137 W265 WSupervisor 2 Enhanced (N77-SUP2E)
110 W150 WSupervisor 3 Enhanced (N77-SUP3E)
1 to 8 (can mix
types)
F2 I/O Modules
451 W500 W48-port 1- and 10-Gigabit Ethernet I/O module
(N77-F248XP-23E)
F3 I/O Modules
450 W
480 W48-port 1- and 10-Gigabit Ethernet I/O module
(N77-F348XP-23)
650 W740 W24-port 40-Gigabit Ethernet I/O module
(N77-F324FQ-25)
640 W730 W12-port 100-Gigabit Ethernet I/O module
(N77-F312CK-26)
F4 I/O Modules
730 W
1000 W30-port 100-Gigabit Ethernet I/O module
(N77-F430CQ-36)
M3 I/O Modules
500 W
560 W48-port 1- and 10-Gigabit Ethernet I/O module
(N77-M348XP-23L)
700 W750 W24-port 40-Gigabit Ethernet I/O module
(N77-M324FQ-25L)
800 W1095 W12-port 100-Gigabit Ethernet I/O module
(N77-M312CQ-26L)
122 W150 W3 to 6Fabric Modules (N77-C7710-FAB-2)
120 W150 W3 to 6Fabric Modules (N77-C7710-FAB-3)
Fan Trays
Cisco Nexus 7710 Switch Site Preparation and Hardware Installation Guide