EasyManuals Logo

Clack WS1CS User Manual

Clack WS1CS
20 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #5 background imageLoading...
Page #5 background image
WS1CS & WS1.25CS Manual Page 5
Table 4 shows the order of the cycles when the
valve is set up as a lter. If the control valve is set
to regenerate for a lter, the OEM has the option
of having the regenerant re ll after the rinse cycle
or have the regenerant pre ll before regeneration.
If the OEM chooses to have the regenerant pre ll
before regeneration, the pre ll starts two hours
before the regeneration time set. During the
2-hour period in which the regenerant is being
made, treated water is still available. For example:
regeneration time = 2:00 am, pre ll option
selected, down ow lter. Fill occurs at 12:00 a.m.,
start of backwash cycle occurs at 2:00 a.m.
When the control valve is used as a non-
regenerating lter, the OEM has the option to
specify one backwash or two backwashes. If two
backwashes are speci ed, two rinses occur. Tables
5 and 6 show the length of the cycles when the
valve is set up as a lter. When used as a non-
regenerating lter, the down ow piston must be
installed, the regenerant piston removed, injector
plugs must be installed in both the DN and UP
injector locations and the re ll elbow must be
replaced with a re ll port plug.
NOTE: The program codes listed on this page
and the following page should be used only as a
guideline. Any program code listed can be applied
to a softener or lter application for WS1CS
valves.
Program
Code
Main Piston
1
st
Backwash
Brine/Slow
Rinse
2
nd
Backwash
Fast
Rinse
P1 Down Flow 3 40 3 3
P2 Down Flow 3 45 3 3
P3 Down Flow 4 45 4 3
P4 Down Flow 4 60 4 3
P5 Down Flow 5 60 4 4
P6 Down Flow 5 60 5 4
P7 Down Flow 6 45 4 3
P8 Down Flow 6 60 5 4
P9 Down Flow 6 60 6 5
P10 Down Flow 7 50 5 4
P11 Down Flow 7 60 6 6
P12 Down Flow 7 65 7 7
P13 Down Flow 8 45 5 4
P14 Down Flow 8 60 6 6
P15 Down Flow 8 60 8 8
P16 Down Flow 8 65 8 6
P17 Down Flow 8 65 8 7
P18 Down Flow 8 75 8 5
P19 Down Flow 9 50 5 5
P20 Down Flow 9 60 5 4
P21 Down Flow 9 65 8 5
P22 Down Flow 10 45 4 4
P23 Down Flow 10 60 5 4
P24 Down Flow 10 65 8 8
P25 Down Flow 10 65 6 5
P26 Down Flow 10 75 7 5
P27 Down Flow 12 45 4 4
P28 Down Flow 12 60 6 4
P29 Down Flow 12 60 8 8
P30 Down Flow 12 65 6 6
P31 Down Flow 12 65 8 8
P32 Down Flow 12 65 12 8
P33 Down Flow 12 75 6 6
P34 Down Flow 14 45 5 4
P35 Down Flow 14 60 6 5
P36 Down Flow 14 60 8 8
P37 Down Flow 14 65 7 6
P38 Down Flow 14 65 8 8
P39 Down Flow 14 65 12 8
P40 Down Flow 14 75 8 7
P41 Down Flow 16 60 7 5
P42 Down Flow 16 65 8 6
P43 Down Flow 16 65 8 8
P44 Down Flow 16 65 12 8
P45 Down Flow 16 75 9 7
P50 Down Flow 6 45 3 3
P51 Down Flow 8 60 8 4
P52 Down Flow 8 75 10 6
Table 2
Down ow Softener Program Codes for WS1CS or WS1.25CS

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Clack WS1CS and is the answer not in the manual?

Clack WS1CS Specifications

General IconGeneral
BrandClack
ModelWS1CS
CategoryControl Unit
LanguageEnglish

Related product manuals