7.3.
Initial start-up
1. Check that all connections are made as specified in
par.4.;
2. close the nitrogen line downline of the generator;
3. switch on the generator, by setting the POWER switch to ON
(par. 7.4.);
4. start nitrogen production by pressing the START key
(par. 7.5.);
5. wait approximately 15 minutes, until the generator reaches the Stand-By
status. In this state, the generator suspends normal production, showing the
following page:
6. from this point the nitrogen is available for the line, by opening the valve closed
in point 2.
e
WARNING: On initial start-up, the internal nitrogen storage tank will initially con-
tain air. For this reason, the line should be vented with the gas (for approx. 60
minutes) before employing the nitrogen for the application utility.
7.4.
Generator start-up
To switch on the generator, put the start button on the rear of the generator in
position I: the CPU screen lights up.
After the LOGO page is shortly displayed, the GENERATORS LIST page appears
Press on the displayed generator.