Starting report
Reading the objective operating conditions is useful
for checking the unit over time.
With unit of full load, namely in stable conditions
and close to those of work, take the following data:
Tension and general absorptions with unit at full
load
Absorption of varied electrical loads (compressors,
fans, pumps etc)
Temperatures and capacities of different liquid
(water, air) in the inlet and outlet of the unit.
Temperature and pressures on the characteristic
points of the refrigerating circuit (compressor
discharge, liquid, intake).
The readings should be stored and made available
during maintenance.
2014/68/UE PED Directive
2014/68UE PED directive provides instructions for
installers, users and maintenance technicians as
well.
Refer to local actuation norms; briefly and as an
example, see the following:
Obligatory tesng of first system:
• only for the units assembled on site be
installer (e.g. condensate unit + direct
expansion unit)
Commissioning declaration:
• for all units
Periodic checks:
• to be carried out with the frequency indicated
by the Manufacturer (see the “maintenance”
section)
8 START-UP