Project Planning
The following is a typical program and timetable for a CF3000 installation project, once the initial order
has been received:
1. Project Meeting
Installer and user to be present; system specifications, schematic diagram and proposed circuit drawing
to be available. CF3000 Installation and Commissioning Guide to be provided.
2. Equipment Fix
Typically 2 week's notice is required for equipment to be delivered. Cable to be installed and bases/back
boxes to be fitted. Then fire detectors, callpoints, alarm sounders, isolator units and interface units to be
installed.
3. Address Schedule
Schedule of sensor locations to be completed by installer and returned to enable system programming.
4. Auto Learn
Fire panel/repeater panels to be installed and terminated. System to be powered up by installer and auto
learn mode activated (see Auto Learn section). System to be tested and verified by installer, prior to final
commissioning.
5. Final Commissioning
Minimum 2 weeks notice is required from receipt of Address Schedule and Commission request form.
Cooper Fire Service Engineer to attend site implement/oversee the final commissioning procedures (see
Commissioning section), in conjunction with the installer.