9 | Electrical installation
Installer reference guide
116
ERGA04~08E + EHVH04+08SU18+23E
Daikin Altherma 3 R F
4P629090-1C – 2022.08
2 Remove the refrigerant piping cover.
3 Strip insulation (20mm) from the wires.
a Strip wire end to this point
b An excessive strip length may cause electrical shock or leakage
4 Connect the interconnection cable and power supply as follows. Ensure stress
relief by using the wire clamp.
a Interconnection cable
b Power supply cable
c Fuse
d Earth leakage circuit breaker