9 | Electrical installation
Installer reference guide
117
ERGA04~08E + EHVH04+08SU18+23E
Daikin Altherma 3 R F
4P629090-1C – 2022.08
a Wire clamp
5 Reattach the switch box cover.
6 Reattach the refrigerant piping cover. Make sure the cables are routed under
the cover as shown:
7 Connect an earth leakage circuit breaker and fuse to the power supply line.
9.3 Connections to the indoor unit
Item Description
Power supply (main) See "9.3.1To connect the main power
supply"[4120].
Power supply (backup
heater)
See "9.3.2To connect the backup heater power
supply"[4122].
Shut-off valve See "9.3.3To connect the shut-off valve"[4124].
Electricity meters See "9.3.4To connect the electricity meters"[4125].
Domestic hot water pump See "9.3.5To connect the domestic hot water
pump"[4126].
Alarm output See "9.3.6To connect the alarm output"[4127].
Space cooling/heating
operation control
See "9.3.7To connect the space cooling/heating ON/
OFF output"[4128].
Changeover to external
heat source control
See "9.3.8To connect the changeover to external
heat source"[4129].