EasyManuals Logo

Dell PowerSwitch S4128F-ON User Manual

Dell PowerSwitch S4128F-ON
49 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #27 background imageLoading...
Page #27 background image
Figure 19. Two-post center-mount installation
2. Slide the back bracket towards the post. Secure it to the post flange with two user-supplied screws, items 2 and 3.
3. Repeat this procedure for the second rail.
Four-post threaded installation
NOTE: For more installation instructions, see the installation labels attached to the rail assembly.
1. Remove the latch castings from each end of the ReadyRails assemblies. To remove the two screws each latch casting, use a
Torx driver.
Retain the latch castings for future rack requirements.
S4100ON Series installation
27

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Dell PowerSwitch S4128F-ON and is the answer not in the manual?

Dell PowerSwitch S4128F-ON Specifications

General IconGeneral
Product TypeSwitch
ModelS4128F-ON
Uplink Ports4 x 100GbE QSFP28
Power SupplyDual, hot-swappable
AirflowFront-to-back or back-to-front
Jumbo Frame SupportYes, up to 9216 bytes
Latency800ns
ManagementCLI, SNMP, REST API
Dimensions (W x D x H)43.0 cm x 4.3 cm