28
Amplon RT Series
6.2 Tower Mounting
Use the included tower stands to mount the UPS in an upright tower position by
following the steps below.
1
Assemble the tower stands and the tower stand expanders
1
according to the
size of the UPS (see Figure 6-3 & Figure 6-4).
Tower Stand
× 4 PCS
Tower Stand
Expander × 4 PCS
Tower Stand
× 4 PCS
Tower Stand
Expander × 6 PCS
(Figure 6-3: Assemble the Tower
Stands for 5/ 6kVA UPS)
(Figure 6-4: Assemble the Tower
Stands for 8/ 10kVA UPS)
2
Pull out the two panels and the two Delta logo nameplates
2
, rotate
them 90° clockwise
3
and re-insert them (see Figure 6-5).
ESC
BATTERY PACK
3
3
2
2
Delta Logo
Nameplate
× 2
Panel
× 2
(Figure 6-5: Rotate the Two Panels and Two Delta Logo Nameplates)