MAINTENANCE
5-6 15 Jun 12
HyperPoolShaker
Installation (Cont’d)
Fully installed panel. Note downward curve into intimate contact with screen bed
3. Repeat procedure for three remaining screen panels.
SCREEN BED MATERIAL REPLACEMENT
The bed materials (Figure 5-2) should be replaced if inspection reveals damage or deterioration.
To replace any of the bed materials, proceed as follows:
1. Stop feed.
2. Wash off process material from screen bed.
3. Shut down electric power, and lock out and tag out machine.
4. Retract all screen compression pins to release all screen panels.
5. Lift and remove screen panels, and remove and discard defective bed materials.
6. To facilitate installation, apply mild soap solution to new bed material components. Insert bed
materials into corresponding locations.
Figure 5-2. Screen Bed Material Locations