8 Dräger X-am 5100
Use
Charging with charger module and plug-in power pack or
vehicle charging adapter
When the power pack is used (Order No. 83 16 994) up to
5 instruments, or with power pack (Order No. 83 15 635),
up to 2 instruments can be charged at the same time.
The power pack contained in the rechargeable battery and
charging set (Order No. 83 18 785) is suitable for charging
one instrument.
When the vehicle charging adapter is used (Order
No. 45 30 057) it is recommended that each charging
module is supplied separately.
The charging process is carried out analogue to charging
with the multiple charging station.
3.1.2 Replacing the batteries / rechargeable batteries
1. Switch off the instrument if necessary (see "Switching off
the instrument" on page 8).
2. Loosen the screw (2.0 mm hexagon socket) on the power
pack and remove the power pack.
3. Replace the alkaline batteries with new ones or the
rechargeable NiMHy batteries with charged ones – ensure
correct polarity.
4. Completely replace the T4 power pack (with sealed
rechargeable batteries, Order No. 83 18 704 / 83 22 244).
5. Insert the power pack into the instrument and tighten the
screw, the instrument switches on automatically.
After replacing the power pack T4, it is recommended that
a complete charging is carried out.
After the batteries have been replaced:
The settings and data are stored when the battery is
replaced. The sensors warm up again.
3.1.3 Switching on the instrument
1. Press and hold the key for approx. 3 seconds until the
countdown » 3 . 2 . 1 « shown in the display has elapsed.
All the display segments, including the visual, audible
and vibration alarms, are activated for a short time.
The software version is displayed.
The instrument performs a self test.
The next sensor to be calibrated is shown, together
with the days remaining until the next calibration, e.g.
» HCl ppm CAL 20 «.
The time until the bump test interval elapses is
displayed in days, e.g., » bt 123 «.
All alarm thresholds A1 and A2 as well as » « (TWA)
1
and » « (STEL)
1
, are displayed consecutively.
During the sensor warm-up period, the respective
display of the measured value flashes and the special
symbol » « (for warning) is displayed. No alarms are
issued during the sensor warm-up period.
2. Press the key to cancel the display of the activation
sequence.
3.1.4 Switching off the instrument
1. Press and hold the key and key at the same time until
the countdown » 3 . 2 . 1 « shown in the display has
elapsed.
Before the instrument is switched off, the visual, audible
and vibration alarms are activated for a short time.
WARNING
Danger of explosion!
Do not replace the batteries / rechargeable batteries in
areas where there is a danger of explosion.
Do not throw used batteries into fire or try to open them
by force. Dispose of the batteries in accordance with
national regulations.
Batteries / rechargeable batteries are part of the Ex
approval.
Only the following types may be used:
Alkaline batteries – T4 – (not rechargeable)
Duracell Procell MN1500
Alkaline batteries – T3 – (not rechargeable)
Varta Powerone 4006
Varta Powerone 4106
Panasonic Powerline LR6
NiMH rechargeable batteries – T3 – (rechargeable)
GP 180AAHC (1800)
max. 40 °C ambient temperature.
00933280.eps
83 16 994 (100 ... 240 V)
83 15 635 (100 ... 240 V)
45 30 057
0
X-am 5100
HCl ppm
0.0
!
1 Only when activated in the instrument configuration. Delivery status: not
activated.
00633280.eps
1
2
3
+
+
OK
OK