Eaton 93PM UPS 480V Three-Wire 100 kW Frame Installation and Operation Manual 164000227—Rev 07 37
33..33 IInnssppeeccttiinngg aanndd UUnnppaacckkiinngg tthhee UUPPSS CCaabbiinneettss
The cabinet is shipped bolted to a metal and wood pallet (see Figure 12 or Figure 13) with outer protective
packaging material covering the cabinet.
NOTE Startup and operational checks must be performed by an authorized Eaton Customer
Service Engineer, or the warranty terms specified on the product's resources page
become void. See Chapter 11 Warranty for details. This service is offered as part of the
sales contract for the UPS. Contact an Eaton service representative in advance (a
minimum two-week notice is required) to reserve a preferred startup date.
WARNING
The UPS cabinet is heavy (see Table 2). If unpacking and unloading instructions are not closely followed, the
cabinet may tip and cause serious injury or death.
1. Carefully inspect the outer packaging for evidence of damage during transit.
CAUTION
Do not install a damaged cabinet. Report any damage to the carrier and contact an Eaton service representative
immediately.
NOTE For the following step, verify that the forklift or pallet jack is rated to handle the weight
of the cabinet (see Table 2 for cabinet weight).
2. Use a forklift or pallet jack to move the packaged cabinet to the installation site, or as close as possible,
before unpacking. If possible, move the cabinet using the pallet. Insert the forklift or pallet jack forks
between the supports on the bottom of the pallet (see Figure 8 or Figure 9 for the UPS cabinet center of
gravity measurements).
CAUTION
Do not tilt the UPS cabinet more than 10° from vertical or the cabinet may tip over.
3. Set the pallet on a firm, level surface, allowing a minimum clearance of 3m (10 ft) on each side for
removing the cabinet from the pallet.
4. Remove the protective packaging material from the cabinet and recycle in a responsible manner. Retain
any parts kits packaged with the cabinet.
5. Inspect the contents for any evidence of physical damage, and compare each item with the Bill of Lading.
If damage has occurred or shortages are evident, contact an Eaton service representative immediately to
determine the extent of the damage and its impact on further installation.
NOTE While waiting for installation, protect the unpacked cabinet from moisture, dust, and
other harmful contaminants. Failure to store and protect the UPS properly may void the
warranty.