The compressor unit must be inspected prior to instal-
lation since components could have come loose and/or
damaged during shipment or moving.
Check for loose bolts, particularly the compressor
and motor mounting nuts.
Check for bent or damaged components. The com-
pressor unit should have also been inspected prior to
off-loading, see Delivery Inspection.
Check that the nitrogen pressure is still holding pres-
sure. The pressure gauge is located at the discharge
bleed valve on the block and bleed assembly. Any
leaks must be xed and the system purged and re-
charged with dry nitrogen.
Look into the suction and discharge connections and
inspect for any signs of corrosion on parts.
Prelube the compressor with the main oil pump and
rotate by hand several revolutions prior to start.
Notify Vilter™ Service and Warranty Department
when the compressor is started.
NOTE
For Pre Start-Up and Start-Up checklists, please
contact Vilter Service and Warranty Department.
CAUTION
Before installation, follow the proper procedures to
depressurize the compressor.
Recommended On-site Tools
The tools recommended to have on site are important
for troubleshooting, inspections and compressor unit
operation. Besides general mechanic tools, these tools
are recommended:
Oil Pump (maximum of 2-3 GPM with motor ap-
proved for Division 1 or Division 2 and with ability to
overcome suction pressure) (VPN A40849A)
Infrared Heat Gun
Torque Wrenches (with ranges from 0 to 600 ft-lbs)
Sockets and wrenches up to 2-1/2” (63.5 mm)
Voltmeter