Product Specification for RBS 2301
4.7.10 Installation
A quick and easy installation procedure is provided. If the installation
preconditions are met, the RBS can be installed in less than 30 minutes.
A minimum of tools and instruments are required when installing an
RBS.
Preconditions
The initiation of the BSC is prepared
The transport network available
1)
at the site
Mains power available at site
Preinstalled antennas and feeders are available
1)
Wall fixture preinstalled
Friendly geographic location and environment (means higher than
-10
C, no precipitation and easy access to the site)
1)
"available" means: accessible and with specified function.
Installation Scenario
To support the idea of a quick and smooth installation scenario, the
RBS installation work can be divided in to two steps:
Preinstallation. Installation of the Mounting Base, antennas and
all necessary cabling ( AC mains, transmission and alarms).
Installation and Commissioning. Installation of the Cabinet
including all parts according to customer ordering.
However the installation is possible to carry out in one site visit.
The manual operations at installation are few and easy, this is valid also
when connecting external cables.
There is no need for an OMT on site, during installation work.
Site Installation Requirement
When installing more than one RBS at the same site, the RBS’s must
be separated. The separation is necessary because of antenna isolation
requirements and to provide sufficient working space.