5.3 INSTALLING THE BARRIER BODY
RISKS
PERSONAL PROTECTIVE EQUIPMENT
F
Perform the operations when there is no electrical power.
!
Before you start, make sure that the plinth's concrete
has solidified.
In this phase the barrier must be locked.
Never manage the barrier by holding the board holder.
1. (10) Remove the 4 nuts with washers from
the plate
2. (11) Place the barrier body on the foundation,
at the four fixing points.
!
Be careful not to damage the electrical cable tubes.
3. (12) Fix the body of the barrier in post ion us-
ing a nut with washer on every fixing point of the
foundation.
!
Use the torque wrench to tighten to the torque shown
in the figure.