D 41 35
1.7 Interrupting/terminating operation
During breaks in paving (e.g. delay due to material trucks)
- Determine the approximate duration.
- When cooling down of the material below the minimum paving temperature must be
expected, run the paver finisher empty and create an edge like the end of a layer.
- Set the drive lever (13) to the centre position.
During longer breaks (e.g. lunch break)
- Set the drive lever (13) to the centre position and the speed adjuster (15) to minimum.
- Switch off the ignition (11).
- Switch the screed heater system off.
- With a screed with gas heating system (o), close the bottle valves.
A
The screed must be heated up to the correct paving temperature before paving may
be restarted.