27
Installation and Operation Manual
System 2000
Normal Operation Summary
How to
1. Turn FoamPro system on.
Action
1. Operate the apparatus engine
to develop hydraulic pressure.
Turn the FoamPro Main Power
circuit breaker switch on. FRC
or HYPRO will appear on the
display momentarily.
2. Make foam solution.
3. Read the total amount of
water flowed during the
operation.
4. Read % of concentrate.
5. Change the % of concentrate.
Display
2. Establish water flow to the foam
capable discharge. The Digital
Display Control Module will
indicate the water flow rate. Press
the FOAM button (red upper-left
button). The LED lamps below the
ON and FLOW labels will illuminate
and the lamp below the ON label
will flash. The rate of water flow will
be displayed in units per minute.
3. Press the SELECT button
(white upper-right button)
until the LED lamp below
the TOTAL WATER label is
illuminated. The total amount of
water will be displayed. Reset
this value to zero by pressing
the t and s buttons at the same
time.
4. Press the SELECT button
(white upper-right button)
until the LED lamp below the
% label is illuminated. The
display will read percentage of
foam concentration. Foam will
continue to be injected.
5. Press the or button. The
display will show the new
concentrate injection rate
chosen. The proportion of
concentrate injected will
change immediately.
Normal Operation Summary Continued on Next Page
660
1920
PC 3.0
PC 6.0