5 | Assembly
30 M2320121_en | Installation instructions Pellet boiler PECO
5.6 Setting up in the boiler room
5.6.1 Moving the boiler in the boiler room
r Position a forklift or similar lifting device with a suitable load-bearing capacity at the
base frame
r Lift and transport to the intended position in the installation room.
Ä Pay attention to the operating and maintenance areas of the equipment in the
process!
5.6.2 Operating and maintenance areas of the equipment
▪ The system should generally be set up so that it is accessible from all sides allowing
quick and easy maintenance.
▪ Regional regulations regarding necessary maintenance areas for inspecting the
chimney should be observed in addition to the specified distances!
▪ Observe the applicable standards and regulations when setting up the system.
▪ Observe additional standards for noise protection!
(ÖNORM H 5190 - Noise protection measures)
Operating and maintenance areas
15-20 25-35
A 600 mm
B 300 mm
C 300 mm
C1 250 mm
C2 750 mm 790 mm
D 100mm
E 500 mm
1)
1. Maintenance area to expand the WOS springs upwards