Assembly | 5
M2320121_en | Installation instructions Pellet boiler PECO 41
5.9 Electrical Connection
DANGER
When working on electrical components:
Risk of electrocution!
When work is carried out on electrical components:
r Always have work carried out by a qualified electrician
r Observe the applicable standards and regulations
Ä Work must not be carried out on electrical components by unauthorised persons
r Flexible sheathed cable must be used for the wiring; this must be of the correct size to
comply with applicable regional standards and regulations
r Release the cover by undoing the retaining screws
r Lift the cover on the front edge slightly and remove it towards the front
r Undo the screws on the top and remove the side panel
r Run the cables of all components through cut-out (A) in the back panel to the
controller and plug in to the following boards