68
6. Operation and Maintenance
This chapter describes maintenance and troubleshooting after starting system operation.
Checking the Power Synchronized Unit Status
Check the LEDs on the power synchronized unit regularly.
Device Replacement After Operation Startup
This section explains the procedure to replace devices after starting system operation.
Replacing a Server
Replacing a Power Synchronized Unit
Replacing an AC Sensor Unit
Replacing a Server
The following procedure provides an overview of the required work to replace a server, such as when a server fails.
Refer to the relevant manuals for more details.
Procedure
1 Replace the server.
2 Perform the necessary settings for the replacement server.
3 Connect the replacement server to the server UPS unit.
End of procedure
After the procedure is complete, check that power synchronization performs normally if necessary.
CAUTION
Do
Ask your maintenance engineer to replace devices.