CHAPTER 4: ELECTRICAL INSTALLATION INSTRUMENT POWER CONNECTIONS
EPM 9450/9650 ADVANCED POWER QUALITY METERING SYSTEM – INSTRUCTION MANUAL 4–5
4.4 Instrument Power Connections
The EPM 9450/9650 meter requires a separate power source.
To use AC power:
1. Connect the line supply wire to the L+ terminal
2. Connect the neutral supply wire to the N- terminal on the meter.
To use DC power:
1. Connect the positive supply wire to the L+ terminal.
2. Connect the negative (ground) supply wire to the N- terminal on the meter.
Power supply options and corresponding suffixes are listed in the table below.
Do not ground the unit through the negative of the DC supply. Separate grounding
is required.
Externally fuse the power supply with a 5 Amp @250V rated slow blow fuse. GE
recommends that you fuse both the L+ and N- connections for increased safety,
but if you are fusing only one connection, fuse the L+ connection.
Use at least 14 Gauge supply wire for the power supply and ground connections.
Note
NOTE ON CORRECT METER FUNCTIONING:
The EPM 9450/9650 meter has a Heartbeat LED, located on the top, right side of the meter
face. When the meter is functioning correctly, the red LED pulse toggles on and off (blinks)
5 times per second. If the meter is not functioning correctly, the Heartbeat LED slows to
one pulse per second
Control Power Option Suffix
18-60 Volts DC D
90-276 Volts AC/DC D2