GE Innova Series - Grouting and Mounting Procedures

GE Innova Series
54 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Item Qty Effectivity Part# Manufacturer
Floor plate / Base plate
Assembly
1 - 2285632 -
2.4 Procedure
2.4.1 Grouting Procedure Installation
The principal reason for grouting is to provide a level surface for the installation of equipment. This
will prevent distortion of the mounting structures and the operational problems resulting from a not
level condition. It, therefore, is very important the grouting procedure be carefully followed and the
pad be level to ensure proper operation of the equipment.
2.4.1.1 Tools and Materials
NOTICE
The relationship between the table base and the positioner base plate is critical.
Prior to drilling mounting holes contact local GE Medical Systems installation
specialist or lead field engineer to verify that the proper full size floor mounting
template is used.
1. Assure the following tools for grouting:
1/2” heavy-duty double-insulated electric drill, 650 rpm or greater
Ardex T-1 Mixing Paddle, to be used with drill
Ardex T-4 Spreader, for the installation of Ardex K-15
Ardex T-5 Smoother, for feather-edging and touch-up work
25 lb (11.4 kg) scale for weighing grout
Quart (0.95 liters) jar for measuring water
Machinist Level (accuracy within .005 inch/foot) (1 part in 2400)
Ten gallon (38 liters) container
Knife and scraper
Sponge or cloth rags
1/4 inch weather stripping
Double sided tape
2.
Assure the following materials for grouting:
Ardex P-51 Primer for preparation of concrete floors
Single Plane and Biplane Innova Systems Pre–Installation Kit Installation Procedures
GE Healthcare Direction 2290880-12-1EN, Revision 1
Chapter 1 Installation Procedure 21