IRECTION 5745295-1EN, REVISION 1 OPTIMA CT520 DOD IB UPGRADE INSTRUCTION
Page 22 Chapter 2 - Upgrade Procedure
Section 2.0
NIO16 Console Upgrade
2.1 Old Console (Z800) Removal
NOTICE Make Sure to follow all Lockout/Tagout requirements while performing this procedure.
1.) Move the cradle all the way out of the gantry and lower to its lowest point.
2.) Shut down the system and power off the Operator Console power switch.
3.) Switch OFF the breaker in the Power Distribution Box (hospital supply).
Note: If there is UPS, switch OFF the UPS output.
4.) Visually verify proper labeling of each cable and disconnect all console rear cables.
5.) Disconnect the cables between the old console and system (Gantry, PDU and local hospital
network).
6.) Remove the old OC aside.