SecoGear 24kV-27kV Air Insulation Switchgear
23
Routine inspection includes:
Check compartment doors are closed properly
Verify the control voltage, auxiliary voltage and battery
voltage are in normal condition
The status indication and position indication for the circuit
breaker and earthing switch etc are normal
Check ammeter and voltmeter on the display
Check relay indications. (The power indication should be on
and fault indication
should be o.)
Check alarm and pre alarm indications
Partial discharge should not occur on the surfaces of
equipment at operating voltage. This can, for example, be
detected by characteristic noises, a clearly perceptible smell
of ozone, or visible glowing in the dark;
Check the heater condition, if installed. The relay monitoring
the heater current is in the low voltage compartment. Check
th
e heater circuit if the red current indication turn o due to
the heater losing power supply. (see gure 5/1)
Heater current
indication
Figure 5/1: Heater current monitoring relay
If any abnormal condition is found, then the cause must be
identied in order to restore normal condition.
Service
Safety measure: The power must be shutdown before
scheduled switchgear service, and the work area
must be isolated. Measures must be taken to disallow
the power being switched on. Ensure proper earthing
and padlocks in place. Specially trained personnel are
required to supervise.
It is recommeded to inspect the circuit breaker every 6
months if in stand-by for a signicant period of time.
The purpo
se for the service is to guarantee the operation quality
of the switchgear and avoid any possible malfunctions. This
increases the life of the switchgear. The scope of work is as
follows:
Inspection: Determination of the actual condition
Servicing: Measures to preserve the specied condition
Repair: Measures to restore the specied condition
The service interval for the switchgear depends on ext
ernal
factors including the operating environment, the operation
frequency and service age etc.
It is recommended to have switchgear serviced
every 2-3 years, if installed in good environment and
not frequently operated.
It is recommended to have switchgear serviced
every year, if operated more than 10 times a month.
It is recommended to have switchgear serviced
every half year, if installed in adve
rse environment
and frequently operated.
It is recommended to have the circuit breaker
replaced, if reached its mechanicall operating cycles
or rated short circuit breaking times.

Table of Contents

Other manuals for GE SecoGear

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the GE SecoGear and is the answer not in the manual?

GE SecoGear Specifications

General IconGeneral
BrandGE
ModelSecoGear
CategorySwitch
LanguageEnglish

Related product manuals