CONDUIT FOR ELECTRICAL
SUPPLY FOR PUMP
JUNCTION BOX
ELBOWS = 2 TO 4 MAX.
50 mm INTERNAL
DIAMETER
SUCTION PIPE
THIS END OF TANK TO
PITCH DOWN APPROX. 50 mm
STORAGE TANK
RECOMMENDATION AT LEAST
10 mm RISE PER METER FOR
THIS SECTION
VENT PIPE
SCREEN VENT PROTECTOR
APPROVED TYPE VENT CAP
WATER TIGHT
LOCK BOX
DISCHARGE SIDE
OF PUMP
SUCTION LINE
CONNECTED TO PUMP SYSTEM
PUMP
FILL PIPE
TYPICAL INSTALLATION DIAGRAM
DEPTH OF PIPE AT
THIS POINT SHOULD
BE MINIMUM OF 0.45 m.
"V"=3.5m
IMPORTANT:
RECOMMENDED INLET PIPE DIAMETER= 50 mm ID
HORIZONTAL PIPE LENGTH "H" = 20 Meters Maximum
DEAD STOCK D = 200MM MINIMUM.
NOTE :
100 mm FROM
BOTTOM OF TANK
DEAD STOCK D
"H"
DETAIL VIEW A
SPECIFIED CONDITION FOR SUCTION LIFT =3.5METER
FUEL TYPE
PURE
GASOLINE
E5 E10 E15
MAX MIN MAX MIN MAX MIN MAX MIN
ALTITUDE METER
2200 400 1400 100 1500 100 1600 100
BEND QUANTITY
4242 4 242
A
EARTHING PROVISIONS IN ACCORDANCE WITH
NATIONAL REGULATIONS.
SUCTION PIPE SHOULD HAVE CONTINUOUS.
THOUGH NOT NECESSARILY UNIFORM PITCH
FROM PUMP TO TANK.
GASOLINE OF RELATIVELY HIGH REID VAPOUR
PRESSURE OR EXCESSIVELY HIGH TEMPERATURES
WILL AFFECT THE DELIVERY RATE OF THE SYSTEM.