Operation
24 3A3489T
Standby
1. Close the abrasive ball valve (J).
2. Turn the selector valve (T) to OFF.
3. Open the pot dump valve (F) until the pot pressure
gauge (H) reaches 0 psi.
Shutdown
1. When you have finished blasting, use the wash
feature to flush all of the abrasive from the blast
hose. See Use the Wash Feature, page 23.
2. Turn the selector valve to OFF, and with the
abrasive ball valve closed, continue to blast until
water is cleared from the hose. This is to dry the
inside of the hose for storage.
3. Perform Pressure Relief Procedure, page 17.
NOTICE
To prevent material from packing out and damaging
the blast hoses, do not shut off your air compressor
during Standby.
WLD
J
WLD
WLD
0 psi
(0 bar)
F
H
NOTICE
To prevent material from packing out and damaging
blast hoses, ensure that the abrasive ball valves are
fully closed before shutting off your air compressor.
WLD

Other manuals for Graco EcoQuip 2 EQm

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Graco EcoQuip 2 EQm and is the answer not in the manual?

Graco EcoQuip 2 EQm Specifications

General IconGeneral
BrandGraco
ModelEcoQuip 2 EQm
CategoryWater Pump
LanguageEnglish

Related product manuals