Operation
3A4802D 17
Refilling the Pot with Abrasive
1. Close the abrasive ball valve (M).
2. Turn the selector valve to OFF.
3. Open the pot dump valve (J) to drain water from the
pot.
NOTE: Be prepared to capture the water that will be
drained from the pot. All disposals must comply with
national, state, and local regulations.
4. Add the abrasive (see Technical Specifications,
page 45 for capacity information) and continue to
step 7 from Setting Up the Equipment, page 12.
Shutting Down
1. When you have finished blasting, perform wash until
all of the abrasive is flushed from the blast hose
(see Using the Wash Feature, page 16).
2. Turn the selector valve to OFF, and with the abra-
sive ball valve closed, continue to blast until all
water is cleared from the hose. This is to dry the
inside of the hose for storage.
3. Perform Pressure Relief Procedure, page 7.
WLD
M
ti30725a
WLD
J
ti30725a

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Graco EcoQuip 2 EQp and is the answer not in the manual?

Graco EcoQuip 2 EQp Specifications

General IconGeneral
BrandGraco
ModelEcoQuip 2 EQp
CategoryIndustrial Equipment
LanguageEnglish

Related product manuals