7.7 Check after Installation
1. Sealing
According to the requirements of the design and protection level, plug the openings for the
AC incoming cables at the bottom of the cabinet with fireproof mud to prevent insects or
dirt from entering the cabinet.
2. Clean up
Clean up the sundries inside the cabinet and around the cabinet, such as cables, binding
tapes, screws, etc. Do not leave installation tools on site or in the cabinet.
3. Check
Check whether the base is firmly installed;
Check whether the electrical connections and cables are correct and complete, whether
the connections are reliable, and whether the grounding is reliable;
Check appearance, marking, cleanliness.