64
Measure relief valve
pressure
Oil
gauge
Pipe joint
Leakage, loosen,
fracture, deformation
and damage condition
Replace pipe
×
12years
Electrical system periodical maintenance schedule
Check
item
Service required
Tools
Daily
(8 hrs)
One and a
half
Monthly
(250hrs)
3months
(500hrs)
Semi-annual
(1000hrs)
Annual
(2000hrs)
Starting
motor
Pinion engagement
condition
Battery
Electrolyte fluid level
and clean
Check electrolyte
proportion
Areometer
Wire
Wire harness damage
and fix loosen
condition
Circuit joint looseness
condition
Steering
indicator
light
Work and installation
condition
Horn
Work and installation
condition
Light and
bulb
Work and installation
condition
Reversing
buzzer
Work and installation
condition
Instrument
Instrument working
condition
Lifting system periodical maintenance schedule
Check
item
Service required
Tools
Daily
(8 hrs)
One and a
half
Monthly
(250hrs)
3months
(500hrs)
Semi-annual
(1000hrs)
Annual
(2000hrs)
Chain,
chain
wheel
Check chain tensity, if
transform, damage or
rust.
Add oil to the chain
Riveting pin and
looseness