5 Pre-Commissioning
Prior to the on-site commissioning of the system by a Hanwell Solutions Technician, the
following items should be prepared by the Customer’s electrical contractors:
Standalone MS1000 Systems
The MS1000 Control Unit(s) case(s) should mounted in position and drilled as
required for cable entry.
The required number and type of Output Cards should be mounted on the
MS1000 Control Unit’s DIN rail.
Mains power run should be run from a mains fused spur into the MS1000 Control
Unit’s case, but not connected.
All necessary control cables should be run from the BMS/plant to the MS1000
Control Unit’s case, but not connected. Cables must be clearly labelled.
Monitoring and Control Systems
The MS1000 Control Unit(s) case(s) should be mounted in position and drilled as
required for cable entry.
Output Cards should be mounted on the MS1000 Control Unit’s DIN rail.
Mains power should be run from a mains fused spur into the MS1000 Control
Unit’s case, but not connected.
A, Customer supplied, Bus cable should be run from the MS1000 Control Unit’s
case to a Junction Box adjacent to the CR2/SR2 Controller. See Section 7.3.2.
All necessary control cables should be run from the BMS/plant to the MS1000
Control Unit’s case but not connected. Cables must be clearly labelled.
A mains socket and PC must be available in the CR2/SR2 Controller’s planned
location.
If any of the pre-commissioning requirements have not been fulfilled, resulting in extra cost to
Hanwell Solutions, the additional costs will be passed on to the Customer, in addition to any
previously quoted commissioning costs.