ASSEMBLY INSTRUCTIONS
PH-300 VERTICAL LIFTING PLATFORM
IM-560en
Vers. 05
Page 23
19 Bring the platform up to the upper landing level and verify that the oor and the wall
on the upper access are parallel.
20 In case some adjustment is necessary, loosen all the guide rail xations, adjust
using the supports, and tighten the xations again using the indicated torque.
21 Drill the oor on the lower end of the guide using the holes in the guide as a
template.
22 Blow the holes and ll them from the bottom towards the outside, with 2 strokes
of the pistol. Immediately insert the M8 threaded rods with the corresponding nuts
and washers to prevent the hardening of the resin. In case an upper landing door is
supplied, it is recommended that this operation be carried out at the same time as
the xation of the door.
23 Wait for an hour without touching the threaded rods until the resin hardens
denitely. Tighten the nuts with a maximum torque of 5 Nm.