Maintenance | 8
Hidrostal AG 29 / 49
8 Maintenance
WARNING
Unsafe behaviour.
Incorrect operation because of insufficient qualifications and knowledge.
Risk of severe injury!
Observe the information and personnel requirements in chapter Safety
requirements [8].
WARNING
Contact with infectious substances.
Risk of severe illness!
Obtain binding information about the hazards relating to the medium from
the operator of the plant.
Wear personal protective equipment.
Thoroughly clean the pump.
Carefully dispose of liquid drained from the oil chamber.
Thoroughly clean tools after use.
WARNING
Work at the pump location, noise from neighbouring pumps, tank
overflowing.
Risk of injury!
Risk of permanent health damage!
Always wear hearing protection near running pumps.
Before entering a tank, make sure at the control console that the tank will
not be flooded during the work.
8.1 Maintenance schedule
Interval Maintenance work Personnel
initially after approx.
1000oh (operating
hours)
Check pump for damage, see chapter Visual inspection
[31]
Instructed persons
(operators)
Check oil level, see chapter Checking the oil [35] Trained personnel
annually Check pump for damage, see chapter Visual inspection
[31]
Instructed persons
(operators)
Check the electric motor, motor cover, cable inlet and
cable for any damage and resistance-free connection, see
chapter Visual inspection [31]
Qualified electricians