8.5 Measures after completion of work
The following steps are to be executed following completion of maintenance
work and prior to switch-on of the system:
1. Check all screw connections that were previously loosened for tightness.
2. Check if all protective devices and covers that were previously removed
are properly installed again.
3. Ensure that all tools, materials and other equipment used have been
removed from work area.
4. Clean work area and device and remove any escaped substances, such
as liquids, processing material or the like.
5. Ensure that all safety devices of the system function properly.
6. Ensure that no persons are in the danger zone.