42 www.honeywell.com
NetAXS™ NX4S1 Installation
NetAXS™ Startup
6.0 NetAXS™ Startup
6.1 LED Operation
When the panel wiring is complete, turn on the power. It might take a few minutes for the panel to
complete the power-up sequence. When the board does initialize, verify that the appropriate LEDs
identified in the following figure are in accord with the descriptions in Table 5 on page 43.
Figure 32: System, Relay and Power LEDs
Ethernet Status
LEDs
Host RS232 and
Downstream LEDs
RS485 LED
RDR 1
RDR 2
Relay Status
LEDs
Relay
Status
LEDs
Power
Run LED
RDR 3
RDR 4