Pre-Installation Manual for i-Series Machines v387 Machine Arrival 2-1
MACHINE ARRIVAL
Upon machine arrival, please complete the following instructions to place the machine at
the installation site (see the appropriate section for detailed information):
1. Inspect the machine upon arrival.
2. Lift machine off the truck or transporter.
3. Move machine near permanent location.
4. Remove auxiliary equipment from pallet.
5. Lift the machine from the pallet.
6. Place the machine on the pads.
7. Rough level the machine.
Follow all local regulations for safe handling of machinery.
Do not remove any bracing on the machine.
Do not remove equipment from inside the machine.
Do not remove auxiliary equipment from a second pallet, if
equipped.
Do not remove or install the console.