Chapter 3 Mechanical and Electrical Installation
-24-
Note: When the inverter power is not higher
than 22kW, the A size can be omitted. When
the inverter power is higher than 22kW, the A
size shall be higher than 50mm.
Note:When inverters are
distributed up and down, mount
splitter for heat insulation as shown
in the diagram.
Heatsink shall be taken into account during the mechanical installation. Due attention shall
be paid to the following items:
1) Install the inverter vertically so that the heat may be expelled from the top. However, the
equipment cannot be installed upside down. If there are multiple inverters, parallel installation is
a better choice. Fig.3-1 MD300 Inverter Installation DiagramIn applications where the inverter
need to be installed up and down, please refer to Fig.3-1 “MD300 Inverter Installation Diagram” for
installing heat insulation splitter.
efesotomasyon.com