Commissioning:
The lifting unit is fully installed and all transport locks, e.g. at the sensor, have been
removed.
NOTE
The control unit parameters have been set at the factory. The parameters need not
be changed for commissioning.
6.3.1 Lifting unit with LevelControl Basic 1
DANGER
Control unit cover not closed properly
Danger to life!
▷ After making the tank settings, make sure to close the control unit cover
properly.
▷ Then plug in the mains plug again.
Steps required for commissioning:
1.
Set the parameter for the inlet nozzle to be used (recommended).
2. Connect the rechargeable battery.
3. Check the direction of rotation.
4. Test the lifting unit for correct function and leak-free operation.
Setting the unit to the lowest inlet nozzle used
The switching frequency can be reduced by setting the unit to the lowest inlet nozzle
used. A switch for this setting is provided on the printed circuit board, which can be
accessed after the control unit cover has been opened.
Settings see table below.
Table 10: Possible tank settings
Tank Level of lowest open inlet nozzle DIL switch settings
[mm] DIL 1 DIL 2 DIL 3 DIL 4
U1.60 E
U1.60 D
Horizontal, 100 mm (DN 50) Off Off Off Off
Horizontal, 180 mm Off Off Off Off
Vertical On Off Off Off
U1.100 E
U1.100 D
U2.100 E
U2.100 D
Horizontal, 180 mm Off On Off Off
Horizontal, 250 mm On On Off Off
Vertical Off Off On Off
US1.100 D
US2.100 D
Horizontal, 180 mm On Off On Off
Horizontal, 250 mm Off On On Off
Vertical On On On Off
6 Commissioning/Start-up/Shutdown
28 of 86
mini-Compacta