Preparatory measures
© KEB, 2015-07 COMBIVERT R6-N Page4.1 - 3
4
10
4. Start-up
The following chapter is intended for everybody who has no experience with the KEB power supply and regen-
erativeunits.Itshallallowacorrectenteringintothiseld.Butbecauseofthecomplexapplicationpossibilities
we must restrict ourselves to explaining the start-up of standard applications.
4.1 Preparatory measures
4.1.1 After unpacking the goods
Afterunpackingthegoodsandcheckingthemforcompletedeliveryfollowingmeasuresaretobecarriedout:
Visual control for transport damage
Should any external damages to the KEB COMBIVERT be visible get in tough with your forwarding agent
and return the unit with a corresponding report to KEB.
4.1.2 Installation and Connection
Installation and connection instructions as well as EMC conform installation are found in the instruction manual.
a.) Galvanized surface
b.) The mounting surface of the inverter must be bright.
If necessary, use contact lacquer as protection against corrosion
Connect the earthing strip to central point in the control cabinet
Installation and connection using the example of E-Housing
4.1.3 Checklist prior to start-up
Before switching on the inverter go through the following checklist.