6 Commissioning/Start-up/Shutdown
29 of 64
KWP-Bloc
Horizontal installation
Fig.7: Filling / topping up the oil reservoir — horizontal installation
A Maximum fill level B Minimum fill level
1. Unscrew vent plug 913.
2. Fill in lubricant until the lubricant level indicator lies between the minimum and
maximum markings.
3. Tighten vent plug 913.
Vertical installation
Fig.8: Filling / topping up the oil reservoir — vertical installation
A Maximum fill level B Minimum fill level
1. Unscrew vent plug 913.
2. Fill in lubricant until the lubricant level indicator lies between the minimum and
maximum markings.
3. Tighten vent plug 913.
6.1.3 Shaft seal
Shaft seals are fitted prior to delivery.
Observe the instructions on dismantling (ðSection7.4.5,Page43) or assembly
(ðSection7.5.3,Page45) .