CHAPTER 3: SETTING INTO OPERATION 3-6
ALPHA 538/552
3. ANCHORING TO THE GROUND
Once the bar feeder is in place, and perfectly aligned, it should be anchored to the ground to make it
stable. To accomplish this, 8 anchorage points (A) have been provided.
8 anchorage bolts (B) must be furnished by the client (min. M10 x 100 mm / 1/2" x 4").
Once the anchoring bolts are tightened, check the alignment again, and correct it if necessary.
· Tighten the nuts of the leveling screws.
· Remove the 4 (2+2) shipping screws for the retraction system (C).
C
C
B
A