TABLE 2. JOINT OPERATION, BRACKET 1
INTERVENTION ORDER STATUS OPERATION r10 r15 r12 r16 r23 r24
1) Heat pump
2) Aer r16 minu, boiler
3) Aer further r16 minutes, system in-
tegraon resistence
HEAT+SAN SANITARY 0/1 1 /
Set the
minutes
5/6 2/3
1) Heat pump
2) Aer r12 minutes, system/DHW inte-
graon resistence
HEAT /
HEAT+SAN
HEAT / SANITARY 1 1
Set the
minutes
Set the
minutes
0 3
1) Heat pump
2) Aer r12 minutes, boiler
HEAT /
HEAT+SAN
HEAT / SANITARY 0/1 0/1/2
Set the
minutes
Set the
minutes
3/6 0
1) Heat pump
2) Aer r12 minutes, system/DHW inte-
graon resistence
3) Aer further r12 minutes, boiler
HEAT /
HEAT+SAN
HEAT / SANITARY 1 1
Set the
minutes
Set the
minutes
3 3
1) Heat pump
2) Aer r12 minutes, boiler
3) Aer further r12 minutes, system/
DHW integraon resistence
HEAT /
HEAT+SAN
HEAT / SANITARY 1 1
Set the
minutes
Set the
minutes
6 3
TABLE 3. JOINT OPERATION, BRACKET 2
INTERVENTION ORDER STATUS OPERATION r10 r15 r12 r16 r23 r24
1) Boiler
2) Aer r12 minutes, heat pump
HEAT /
HEAT+SAN
HEAT 0/1 0/1/2
Set the
minutes
/ 1/3/4/6 0/2
1) Boiler
2) Aer r12 minues, system integraon
resistence
3) Aer further r12 minutes, heat pump
HEAT /
HEAT+SAN
HEAT 1 0/1/2
Set the
minutes
/ 1/3 1/3
1) Boiler
2) Aer r12 minutes, heat pump
3) Aer further r12 minutes, system in-
tegraon resistence
HEAT /
HEAT+SAN
HEAT 1 0/1/2
Set the
minutes
/ 4/6 1/3
1) System integraon resistence
2) Aer r12 minutes, heat pump
HEAT /
HEAT+SAN
HEAT 1 0/1/2
Set the
minutes
/ 0/2/5 1/3
1) Boiler
2) Aer r16 minutes, heat pump
HEAT+SAN SANITARY 0/1 0/1/2 /
Set the
minutes
2/3/5/6 0/1
1) Boiler
2) Aer r16 minutes, system integraon
resistence
3) Aer further r16 minutes, heat pump
HEAT+SAN SANITARY 0/1 1 /
Set the
minutes
2/3 2/3
1) Boiler
2) Aer r16 minutes, heat pump
3) Aer r16 minutes, system integraon
resistence
HEAT+SAN SANITARY 0/1 1 /
Set the
minutes
5/6 2/3
1) System integraon resistence
2) aer r16 minutes, heat pump
HEAT+SAN SANITARY 0/1 1 /
Set the
minutes
0/1/4 2/3
1) Boiler
2) Aer r12 minutes, heat pump
HEAT /
HEAT+SAN
HEAT / SANITARY 1 1
Set the
minutes
Set the
minutes
3/6 0
1) Boiler
2) Aer r12 minutes, system/DHW inte-
graon resistence
3) Aer further r12 minutes, heat pump
HEAT /
HEAT+SAN
HEAT / SANITARY 1 1
Set the
minutes
Set the
minutes
3 3
1) Boiler
2) Aer r12 minutes, heat pump
3) Aer further r12 minutes, system/
DHW integraon resistence
HEAT /
HEAT+SAN
HEAT / SANITARY 1 1
Set the
minutes
Set the
minutes
6 3
1) system/DHW integraon resistence
2) Aer r12 minutes, heat pump
HEAT /
HEAT+SAN
HEAT / SANITARY 1 1
Set the
minutes
Set the
minutes
0 3
TABLE 4. OPERATIO IN SUBSTITUTION
INTERVENTION ORDER STATUS OPERATION r10 r15 r12 r16 r23 r24
1) Boiler
2) Aer r12 minutes, system integraon
resistence
HEAT /
HEAT+SAN
HEAT 0/1 0/1/2
Set the
minutes
/ 4/6 1/3
1) System integraon resistence
2) Aer r12 minutes, boiler
HEAT /
HEAT+SAN
HEAT 0/1 0/1/2
Set the
minutes
/ 1/3 1/3
1) Boiler
2) Aer r12 minutes, system integraon
resisitence
HEAT+SAN SANITARY 0/1 0/1/2 /
Set the
minutes
5/6 2/3