10. ELECTRICAL SYSTEM
10-
Removal/installation of main fuse
1、Remove battery negative connection.
2、Remove the main fuse box cover.
3、Disassemble in the order specified in the table。
4、Installation sequence is opposite to disassembly
sequence。
Remove/install fuse box
1、Remove battery anode connection。
2、Remove self-tapping nail for fixing fuse box。
3、Installation sequence is opposite to disassembly
sequence。
Inspection of ignition switches
1、Remove battery negative connection.
2、Open hood cover。
3、Disconnect ignition switch connector。
4、Check the conduction between the terminals of
the ignition switch with an ohmmeter and
replace the ignition switch if it does not meet
the technical requirements renewal
Inspection of backup power
1、Open hood cover
2、Disconnect the backup power connector.
3、Use a voltmeter to check the wire harness end
12 voltage.