To define a daily time period in which a specific battery charging source priority is to be temporarily activated, follow
the steps below:
1. Press and hold for 3 seconds t o enter the timer setting for the battery charger source priority.The three
available priority orders are shown on the display (see chapterDevice Operation Settings Settings
menu 16 for an explanation):
2. From top to bottom the priorities shown in the screen represent:
a. Solar first (“CSO”for Charger Solar)
b. Solar and Utility (“SNU” for Solar and Utility )
c. Only Solar (“OSO”)
3. Press either , or to enter one of the three selectable priorities:
a. = CSO
b. = SNU
c. = OSO
4. The selected priority order (CSO, SNU or OSO) is shown at the topof the screen. The middle shows the
starting time and the bottom shows the s topping time in full hours (24h notation). As an example for the
CSO priority:
5. Press to select the starting time (middle of screen), it will flash. Now press or to change the
starting time in 1-hour steps.Then, press to confirm the s tarting time, it will stop flashing.
6. Press to select the ending time (bottom of screen), it will flash. Now press or to change the
ending time in 1-hour steps. Then, press t o confirm the e nding time, it will stop flashing.
7. Now press to return to main screen.
8.6 Screen Views of Current Values
The screen views can be scrolled by pressing or to show current values in the following order: