Commissioning switch version 0-1-2
1. Remove the cup warmer lid (f). Take out the delivery and discharge pipes
and withdraw the water tank.
2. Fill the water tank (g), with drinking water, softened if possible.
3. Return the water tank to its original position.
4. Switch on the machine bringing the switch (h) to position 1; the light (i)
switches on.
5. Raise the group lever (b) to delivery position, wait until approx. ½ litre of
water pours out from the group (boiler full) then lower the lever.
6. Set the switch (h) in position 2 to start the boiler heating; light (j) on.
7. When the heater light (j) switches off, the machine is ready to deliver the
coffee.
Important: Make sure that the silicon tubes are completely immersed in the
water and are not bent.
Commissioning switch version 0-1
1. Remove the cup warmer lid (f). Take out the delivery and discharge pipes
and withdraw the water tank.
2. Fill the water tank (g), with drinking water, softened if possible.
3. Return the water tank to its original position.
4. Switch on the machine bringing the switch (h) to position 1; the light (i)
switches on. In the case of empty tank, the Termopid display indicates the
letter "A" flashing.
5. Only when the Termopid is first switched on or reset, the display displays the
message "1ST" (First step) and the machine does not heat. To exit from this
condition, raise the lever (b) of the group in the delivery position for at least
30 seconds verifying the water output from the group (full boiler) then lower
the lever. At this point the machine starts to heat, light (j) on, and the display
indicates the temperature of the boiler.
6. When the heater light (j) switches off, the machine is ready to deliver the
coffee.
Important: Make sure that the silicon tubes are completely immersed in the
water and are not bent.